“GDBSB maintains that the purported determination is wrongful as the mandatory contractual procedures and notices prior to the determination have not been complied with,” it said in a statement.
“GDBSB maintains that the purported determination is wrongful as the mandatory contractual procedures and notices prior to the determination have not been complied with,” GDB said in a statement.
Since March 24, GDB has remobilised and recommenced construction works for Tower A only after a total prolonged duration of 220 days for suspension under Clauses 30.7 and 21.4 of the PAM Contract 2006 due to non-honouring of multiple interim certificates by DCSB.
Philippines Latest News, Philippines Headlines
Similar News:You can also read news stories similar to this one that we have collected from other news sources.
Seni Jaya gets 5 + 5 years external advertising contractKUALA LUMPUR: Seni Jaya Corporation Bhd’s wholly-owned subsidiary, Seni Jaya Sdn Bhd has accepted a letter of acceptance (LOA) from Prasarana Integrated Development Sdn Bhd (PRIDE).
Read more »
Pertama Digital inks MoU with Kridentia TechKUALA LUMPUR: Pertama Digital Bhd has signed a memorandum of understanding with Kridentia Tech Sdn Bhd (KTSB) to enhance and secure digital ID for Malaysia.
Read more »
OSK Ventures appoints founder Ong Leong Huat as non-executive chairmanOSK Ventures appoints founder Ong Leong Huat as non-executive chairman FMTNews FMTBusiness
Read more »
South African cannabis firm wins Malaysian backer in new listing bidSouth African cannabis firm wins Malaysian backer in new listing bid FMTNews FMTBusiness
Read more »
Gentari, City Energy to explore Malaysia-Singapore hydrogen supply chainKUALA LUMPUR: Petroliam Nasional Bhd's (PETRONAS) clean energy solutions provider Gentari Sdn Bhd has entered into a memorandum of understanding (MoU) with Singapore's gas utility provider City Energy to conduct feasibility studies of a hydrogen supply chain from Malaysia to Singapore.
Read more »