State Health and Unity Committee chairman Ling Tian Soon expects the project to be completed by the end of next year and be fully operational in 2025 theSun theSundaily hospital healthcare development deadline government Malaysia
: The Pasir Gudang Hospital is expected to be completed ahead of schedule as the work progress on the building is already at 40.47 per cent.
“According to the schedule, the project was supposed to be 27.96 per cent completed as of May 15, but we are 12.51 per cent ahead of schedule and the hospital is 40.47 per cent ready. Ling, who said that the Buddha’s Light International Association, a non-governmental organisation , donated 300 sets of overbed tables and patient bedside lockers estimated at RM300,000 to the Bunga Raya Ward, hopes the Pasir Gudang Hospital, the third government hospital in the district, would help reduce congestion at the HSA and Sultan Ismail Hospital here.
Philippines Latest News, Philippines Headlines
Similar News:You can also read news stories similar to this one that we have collected from other news sources.
Pasir Gudang Hospital expected to be completed ahead of schedule, says Johor excoJOHOR BARU, June 25 — The Pasir Gudang Hospital is expected to be completed ahead of schedule as the work progress on the building is already at 40.47 per cent. State Health...
Read more »
Hospital Pasir Gudang dijangka siap lebih awalHospital Pasir Gudang dijangka siap lebih awal BERITA Komuniti NASIONAL PRIHATIN
Read more »
Johor bincang dengan Orang Asli isu warta Tanah KesultananLangkah tersebut diambil bagi memastikan tiada sebarang provokasi dilakukan pihak tidak bertanggungjawab berhubung isu berkenaan.
Read more »
Johor govt to hold discussions with Orang Asli regarding Sultanate Land, says excoJOHOR BARU, June 23 — Any discussions on the status and suggested gazettement of Orang Asli settlements under Sultanate Land need to be done through roundtable discussions and...
Read more »