The Commission on Audit flagged Cebu City for leaving P413.71 million of Cebu BRT funds unutilized since 2017, with only a 10.11 percent utilization rate.
The Commission on Audit ( COA) flagged the Cebu City Government for leaving P413.71 million unutilized out of the P460.26 million released for the Cebu Bus Rapid Transit (CBRT) project since 2017. In its 2025 Annual Audit Report, COA said the City utilized only P46.55 million, or 10.11 percent, of the total funds. The remaining P413.71 million was left unutilized after more than eight years.
COA said the low utilization rate was inconsistent with Sections 4 and 16 of Presidential Decree (PD) 1445, or the Government Auditing Code of the Philippines, and Section 3 of PD 1870.
Causes of Low Fund Utilization
State auditors attributed the low utilization to operational constraints, including the absence of clearly defined timelines, inadequate manpower and delays in implementing key project components.
These issues significantly impeded the implementation of the CBRT project, particularly the acquisition of road right-of-way (ROW) and project sites. COA said the delays also postponed the realization of the project's intended benefits.
COA Recommendations and City Commitments
COA recommended that Mayor Nestor Archival, through the CBRT Project Management Office (PMO), establish and strictly implement clear timelines and milestones for all remaining work items under the approved program of works.
In response, the Cebu City Government committed to adopt a jointly validated CBRT work program with achievable milestones for every outstanding city responsibility. The CBRT-PMO, Department of Engineering and Public Works, City Planning and Development Office and Department of Transportation (DOTr) are tasked to update the remaining road construction works and site tasks.
They must also identify project dependencies and fund utilization, secure management and DOTr concurrence and set the implementation period from September to December 2026.
COA also recommended that the City provide the CBRT-PMO with adequate technical and administrative support, including additional competent personnel, to speed up the ROW and site acquisition process. Acknowledging the finding, the City committed to assess its BRT technical and administrative staffing gaps and provide authorized support.
The mayor, CBRT-PMO, Human Resource Development Office, City Budget Office and City Legal Office are tasked to prepare a workload and skills plan. They will designate responsible personnel and secure the necessary staffing and funding approvals.
Coordination and Oversight Measures
Another COA recommendation called for stronger coordination between the CBRT-PMO and the DOTr to promptly resolve issues requiring intervention from the national agency. The City committed to maintain a documented issue-resolution process with the DOTr, including regular coordination meetings and an updated decision and impediment log.
COA further recommended the creation of an oversight or monitoring committee to regularly evaluate the CBRT project's progress, timelines and performance and ensure accountability in its implementation. The City committed to establish an authorized CBRT oversight mechanism that includes independent reviews of project progress and expenditures.
The mayor, CBRT-PMO, Local Finance Committee and City Planning and Development Office will be responsible for defining the committee's composition, mandate, milestones and escalation rules, as well as issuing the appropriate order and requiring periodic performance reports.
All four corrective measures were listed as to be implemented as of the audit report.
The CBRT is a major public transport project intended to improve mobility along Cebu City's main transport corridor. However, its implementation faces delays involving ROW acquisition, project sites and coordination among the agencies involved.
COA's latest findings put the City's utilization of the released CBRT funds and its remaining implementation responsibilities under renewed scrutiny as the City works to address the audit recommendations before the end of 2026.
Cebu City Cebu Bus Rapid Transit Commission On Audit COA P413.71 Million Nestor Archival Department Of Transportation
Philippines Latest News, Philippines Headlines
Similar News: You can also read news stories similar to this one that we have collected from other news sources.
Vice Mayor Osmeña to File Ombudsman Complaint Over Cebu BRT Property AcquisitionVice Mayor Tomas Osmeña announces filing a case with the Office of the Ombudsman to challenge the valuation and procurement of F. Vestil Street properties for the Cebu Bus Rapid Transit project, citing concerns of inflated costs, inappropriate commercial acquisition, and a lack of transparency.
Read more »
SM Seaside Cebu Arena creates new reasons to visit, stay, & experience CebuCebu is becoming a destination where there is always another reason to stay a little longer.
Read more »
Gabii sa Kabilin Launches 20th Anniversary Countdown in Cebu CityThe Ramon Aboitiz Foundation Inc. kicked off the 20th anniversary of Gabii sa Kabilin at The Kabilin Center in Cebu City on Oct. 2, 2026, with tours of 10 heritage sites.
Read more »
Cebu City ONE-ACT Enlists Habal-Habal Drivers in Crime Prevention DriveThe Cebu City Police Office forms Cebu City ONE-ACT with habal-habal drivers from 80 barangays, turning them into eyes and ears to fight crime under Police Colonel Ricky Sumalde.
Read more »